The Na Phay-Don Cham Bridge in Nghe An Province, central Vietnam, has completed its main structure but currently lacks access roads at both ends. Photo by Read/Hung Le
A newly built bridge in north-central Vietnam’s Nghe An has been left unusable months after completion, forcing more than 1,000 residents in two highland villages to keep crossing streams on foot or rely on a narrow suspension bridge.
The Na Phay-Don Cham Bridge, which spans a stream linking Thanh Phong 1 and Thanh Phong 2 villages in Que Phong Commune, was completed in mid-2025 with a total investment of more than VND15 billion (US$600,000). Yet the bridge remains closed because access roads at both ends have not been finished.
As a result, around 200 households are still cut off from safe road access. During the rainy season, villagers must wade through fast-rising water to travel between villages, posing serious safety risks.
Local leader Lu Dinh Hieu, head of Thanh Phong 1 village, said residents have no choice but to continue using the old suspension bridge or cross the stream directly because vehicles cannot reach the new bridge.
The unfinished project has also disrupted local trade. Trucks transporting construction materials or collecting farm produce are unable to cross the suspension bridge and must rely on small-scale transshipment, driving up costs. Farmers say crops such as cassava and corn are often bought at lower prices due to difficult transport routes.
Construction of the bridge began in late 2021 and was originally scheduled for completion by the end of 2024. While the main structure was finished in May 2025, the project has reached only about 67% of its contract value, with key components still missing, including railings, earthworks around the abutments and access roads.
According to Que Phong Commune chairman Luu Van Hung, the delay is due to the lack of an approved soil source to build the approach roads, as no suitable quarry currently matches the project’s original approval documents. The commune has repeatedly urged relevant agencies to supply materials so work can continue, but progress has stalled.
The provincial Department of Construction also cited safety issues involving existing power lines and utility poles that do not meet clearance requirements, preventing some remaining work from moving forward. Authorities say they are coordinating with contractors to resolve the issues and complete the project in the coming period.
Contact to : xlf550402@gmail.com
Copyright © boyuanhulian 2020 - 2023. All Right Reserved.